C811 M61 Jn 4 – Cutacre S278 (Case Studies)
A&T Surfacing Ltd.
‘M61 Junction 4 – S278 Highway Works, Bolton’
Contract Value:
£2m
Project:
S278 Highway works for the Logistics North Development at the old Cutacre opencast site off the A6 Trunk Road near Bolton.
Description:
Highway improvements to the M61 Junction 4 roundabout and existing A6 roundabout to improve traffic movements to the large new development. Following on from this works included the surfacing of the new trunk road through the new industrial estate along with associated arterial routes and footpaths.
Client:
Bolton MBC
Supervising Engineer:
Lee Thompson
Bolton MBC,
Environmental Department,
The Wellsprings,
Civic Centre,
Bolton, BL1 1US
Bolton MBC,
Environmental Department,
The Wellsprings,
Civic Centre,
Bolton, BL1 1US
Telephone:
01204 336677





C870 Great Homer St Liverpool (Case Studies)
A&T Surfacing Ltd.
‘Great Homer Street, Liverpool’
Contract Value:
£1.1m
Project:
S278 & S38 Highway works for major retail development on a primary route close to Liverpool City centre.
Description:
The project included the construction of a new S38 link road between Great Homer Street and Scotland Road to serve the new Sainsbury’s Supermarket and retail units, together with S278 highway and junction improvements on Great Homer Street and Scotland Road.
Client:
St. Modwen Developments Ltd. / DBK Partners LLP (now RPS)
Supervising Engineer:
Kevin Theobold
DBK Partners LLP (now RPS Group)
2nd Floor, Carvers Warehouse, 77 Dale Street,
Manchester, M1 2HG
DBK Partners LLP (now RPS Group)
2nd Floor, Carvers Warehouse, 77 Dale Street,
Manchester, M1 2HG
Telephone:
0161 228 1800 (kevin.theobold@rpsgroup.com)





C885 A559 Chester Way Northwich (Case Studies)
A&T Surfacing Ltd.
‘A559 Chester Way / Leicester Street Roundabout, Northwich’
(C885)
Contract Value:
£500k
Project:
Highway construction project.
Description:
The works involved the upgrade of an existing very busy 5 arm roundabout on the outskirts of Northwich to a new gyratory system, utilising the existing highway including carriageways, footways and verge areas and the roundabout to provide additional running lanes, access roads and parking areas. The works consisted of carriageway construction and surfacing works including the laying of a new HRA and pre-coated chippings surface course to the gyratory.
Client:
Cheshire West & Chester Borough Council,
58 Nicholas Street, Chester, CH1 2NP
58 Nicholas Street, Chester, CH1 2NP
Supervising Engineer:
David Wilcock
Telephone:
01244 973880
Dvid.Wilcock@cheshirewestandchester.gov.uk
Dvid.Wilcock@cheshirewestandchester.gov.uk





C891 Pannal Highway Works (Case Studies)
A&T Surfacing Ltd.
‘Dunlopillo Site, Pannal, Harrogate – S278 & S38 Highway Works’
Contract Value:
£500k
Project:
D&C Section 278 & 38 highway and infrastructure works for a new Care Home under construction on green field site off the A61.
Description:
D&C Section 278 Works: Construction of a new roundabout on the existing and busy A61, working off-peak restricted hours on the live carriageway whilst maintaining traffic movement. D&C Section 38 Works: Construction of a new adoptable road from the roundabout to the new care home.
Client:
Rycroft Group (Holdings) Ltd / Projex Building Solutions Ltd
Supervising Engineer:
Dale Dixon
A.E Yates Limited
A.E Yates Limited
Telephone:
07740 393261 (Dale.Dixon@aeyates.co.uk)





C906 Edge Lane Liverpool
A&T Surfacing Ltd.
‘S278 & S38 Highway Works, Edge Lane, Liverpool’
Contract Value:
£1.56m
Project:
Section 278 & 38 highway and infrastructure works for a major new retail development, Liverpool Shopping Park.
Description:
Construction of new highways and footways in high quality materials, alterations to existing highways and footways including extensive PR liaison with local residents, businesses and the travelling public on this very busy primary route in / out of Liverpool city centre. (NEC/ECC Option B)
Client:
Derwent Group / Caddick Construction / A.E. Yates Limited
Supervising Engineer:
Sven Till
Telephone:
07841 605272 (Sven.Till@aeyates.co.uk)





Rochdale Framework 1
A&T Surfacing Ltd.
‘Rochdale Surfacing Framework’
Contract Value:
£5m+
Project:
Rochdale Council Surfacing Framework
Description:
Complete various planning and resurfacing schemes throughout Rochdale in accordance with the Council programme of works
Client:
Rochdale Borough Council
Supervising Engineer:
Jignesh Sohilia
Queens St, Rochdale
Before

After


Rochdale Framework 2
A&T Surfacing Ltd.
‘Rochdale Surfacing Framework’
Contract Value:
£5m+
Project:
Rochdale Council Surfacing Framework
Description:
Complete various planning and resurfacing schemes throughout Rochdale in accordance with the Council programme of works
Client:
Rochdale Borough Council
Supervising Engineer:
Jignesh Sohilia
Windermere Road, Middleton
Before

After


Russell Homes
A&T Surfacing Ltd.
‘RUSSELL homes’
Contract Value:
£65k
Project:
Green Booth Village, Norden
Description:
Lay HRA surface course to the access roads throughout the new housing development.
Client:
Russell Homes